A renovation project involves scraping paint from interior walls of a house built in 1968. The contractor estimates 850 square feet of painted surface will be disturbed. What lead-safe work practice requirements apply?

Correct Answer

A) Both EPA RRP Rule and OSHA lead standard requirements

For pre-1978 housing with more than 6 square feet of painted surface disturbance, both EPA's Renovation, Repair, and Painting (RRP) Rule and OSHA's lead standard apply. The large area (850 sq ft) triggers comprehensive lead-safe work practices.

Answer Options
A
Both EPA RRP Rule and OSHA lead standard requirements
B
EPA RRP Rule requirements only
C
OSHA lead standard requirements only
D
No special requirements needed

Why This Is the Correct Answer

Since the house was built in 1968 (pre-1978) and the project disturbs 850 square feet of painted surface (well above the 6 sq ft threshold), both federal regulations apply. The EPA RRP Rule requires certified renovators and specific work practices for pre-1978 housing when more than 6 sq ft of painted surface is disturbed. OSHA's lead standard also applies to protect workers when lead exposure is reasonably expected, which is the case with extensive paint disturbance in pre-1978 housing.

Why the Other Options Are Wrong

Option C: OSHA lead standard requirements only

While OSHA lead standard requirements do apply for worker protection, EPA RRP Rule requirements also apply since this involves renovation work in pre-1978 housing with paint disturbance exceeding 6 sq ft.

Option D: No special requirements needed

Special requirements are definitely needed because this involves a pre-1978 house with extensive paint disturbance (850 sq ft), which far exceeds regulatory thresholds and creates significant lead exposure risk.

Memory Technique

Use '1978 + 6 = BOTH' - if the building is pre-1978 AND more than 6 sq ft of paint is disturbed, BOTH EPA RRP and OSHA lead standards apply.

Reference Hint

Florida Building Code Chapter 1, Section 105 - Permits Required, and EPA RRP Rule documentation in environmental safety sections

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.