A project requires submission of Pay Application #3 for work completed through February. The contract amount is $500,000, with 10% retainage. Previous payments total $180,000. Work completed to date is $275,000. What is the amount due?
Correct Answer
C) $67,500
Work completed ($275,000) less 10% retainage ($27,500) equals $247,500. Subtract previous payments ($180,000) to get current payment due: $247,500 - $180,000 = $67,500.
Why This Is the Correct Answer
The correct calculation follows the standard pay application formula used in construction contracts. First, calculate the net amount earned to date by taking the work completed ($275,000) and subtracting the 10% retainage ($27,500), which equals $247,500. Then subtract all previous payments received ($180,000) to determine the current payment due of $67,500. This ensures the contractor receives payment for new work while maintaining the required retainage percentage.
Why the Other Options Are Wrong
Option A: $95,000
This amount ($77,500) incorrectly calculates retainage only on the current period's work rather than on the total work completed to date, resulting in an overpayment that would reduce the overall retainage percentage below the required 10%.
Option B: $85,500
This amount ($85,500) appears to subtract retainage from only the new work performed this period ($95,000 - $9,500), rather than calculating retainage on the cumulative work completed, which violates standard retainage practices.
Memory Technique
Remember 'WRAP': Work completed, Retainage subtracted, All previous payments subtracted, Payment due calculated. Always apply retainage to the total cumulative work, not just the current period.
Reference Hint
Florida Building Code, Chapter 1, Section 107 - Fees and Permits, or AIA A201 General Conditions Article 9 - Payments and Completion
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
