A project requires a building permit with a valuation of $850,000. The permit fee structure is $5.00 per $1,000 for the first $100,000, then $3.50 per $1,000 for the remainder. What is the total permit fee?
Correct Answer
C) $3,125
First $100,000: ($100,000 ÷ $1,000) × $5.00 = $500. Remaining $750,000: ($750,000 ÷ $1,000) × $3.50 = $2,625. Total: $500 + $2,625 = $3,125.
Why This Is the Correct Answer
The permit fee calculation uses a tiered structure. For the first $100,000: ($100,000 ÷ $1,000) × $5.00 = $500. For the remaining $750,000: ($750,000 ÷ $1,000) × $3.50 = $2,625. Total permit fee is $500 + $2,625 = $3,125. This correctly applies the different rates to their respective value ranges.
Why the Other Options Are Wrong
Option A: $4,250
This answer incorrectly applies the higher $5.00 rate to the entire $850,000 valuation instead of using the tiered structure. The calculation would be ($850,000 ÷ $1,000) × $5.00 = $4,250, which ignores the lower rate for amounts over $100,000.
Option B: $3,750
This answer appears to use an incorrect rate or calculation method. It doesn't match either applying a single rate to the total valuation or correctly using the tiered structure with the given rates of $5.00 and $3.50 per $1,000.
Option D: $4,500
This answer suggests using an incorrect rate calculation. It's close to applying $5.00 to the first $100,000 and a higher rate to the remainder, but doesn't match the specified $3.50 rate for amounts over $100,000.
Memory Technique
Remember 'First 100 at FIVE, Rest at THREE-FIFTY' - apply $5.00 per $1,000 to first $100,000, then $3.50 per $1,000 to remainder.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
