EstatePass
Business & FinanceRegulationshard15% of exam part

A project requires a building permit with a valuation of $850,000. The permit fee structure is $5.00 per $1,000 for the first $100,000, then $3.50 per $1,000 for the remainder. What is the total permit fee?

Correct Answer

C) $3,125

First $100,000: ($100,000 ÷ $1,000) × $5.00 = $500. Remaining $750,000: ($750,000 ÷ $1,000) × $3.50 = $2,625. Total: $500 + $2,625 = $3,125.

Answer Options
A
$4,250
B
$3,750
C
$3,125
D
$4,500

Why This Is the Correct Answer

The permit fee calculation uses a tiered structure. For the first $100,000: ($100,000 ÷ $1,000) × $5.00 = $500. For the remaining $750,000: ($750,000 ÷ $1,000) × $3.50 = $2,625. Total permit fee is $500 + $2,625 = $3,125. This correctly applies the different rates to their respective value ranges.

Why the Other Options Are Wrong

Option A: $4,250

This answer incorrectly applies the higher $5.00 rate to the entire $850,000 valuation instead of using the tiered structure. The calculation would be ($850,000 ÷ $1,000) × $5.00 = $4,250, which ignores the lower rate for amounts over $100,000.

Option B: $3,750

This answer appears to use an incorrect rate or calculation method. It doesn't match either applying a single rate to the total valuation or correctly using the tiered structure with the given rates of $5.00 and $3.50 per $1,000.

Option D: $4,500

This answer suggests using an incorrect rate calculation. It's close to applying $5.00 to the first $100,000 and a higher rate to the remainder, but doesn't match the specified $3.50 rate for amounts over $100,000.

Memory Technique

Remember 'First 100 at FIVE, Rest at THREE-FIFTY' - apply $5.00 per $1,000 to first $100,000, then $3.50 per $1,000 to remainder.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.