EstatePass
Project MgmtConstructionhard63% of exam part

A project requires 2,400 cubic yards of fill material to be compacted to 95% standard Proctor density. If the borrow material has a shrinkage factor of 15%, how many cubic yards of material must be excavated from the borrow pit?

Correct Answer

B) 2,824 cubic yards

With 15% shrinkage, you need 15% more material than the final compacted volume. Required material = 2,400 ÷ 0.85 = 2,824 cubic yards to account for the volume loss during compaction.

Answer Options
A
2,400 cubic yards
B
2,824 cubic yards
C
2,760 cubic yards
D
2,040 cubic yards

Why This Is the Correct Answer

When material has a 15% shrinkage factor, it means the final compacted volume will be 85% of the original excavated volume. To find the required excavation amount, divide the needed compacted volume by the remaining percentage: 2,400 ÷ 0.85 = 2,824 cubic yards. This accounts for the 15% volume loss that occurs during compaction to 95% standard Proctor density.

Why the Other Options Are Wrong

Option A: 2,400 cubic yards

This assumes no shrinkage occurs, which ignores the 15% shrinkage factor. Using 2,400 cubic yards would result in only 2,040 cubic yards of compacted fill (2,400 × 0.85), falling short of the required 2,400 cubic yards.

Option C: 2,760 cubic yards

This incorrectly adds 15% to the required volume (2,400 × 1.15 = 2,760). This approach fails to account for the fact that shrinkage is calculated from the original excavated volume, not added to the final compacted volume.

Option D: 2,040 cubic yards

This represents what you would get if you excavated 2,400 cubic yards with 15% shrinkage (2,400 × 0.85 = 2,040). This is the result of insufficient excavation, not the amount needed to be excavated.

Memory Technique

Remember 'Shrink and Divide': When material shrinks, divide the needed amount by what remains (100% - shrinkage%). For 15% shrinkage, divide by 0.85.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.