A project requires 15,000 cubic yards of fill material. If trucks can carry 12 cubic yards each and make 3 trips per day, how many truck-days are needed?

Correct Answer

D) 417 truck-days

Each truck carries 12 cubic yards × 3 trips = 36 cubic yards per day. Total truck-days needed: 15,000 ÷ 36 = 416.7, which rounds to 417 truck-days.

Answer Options
A
125 truck-days
B
42 truck-days
C
1,250 truck-days
D
417 truck-days

Why This Is the Correct Answer

Option C is correct because it properly calculates the daily capacity per truck and divides the total requirement by this capacity. Each truck carries 12 cubic yards per trip and makes 3 trips per day, giving 36 cubic yards per truck per day. Dividing 15,000 cubic yards by 36 cubic yards per truck-day equals 416.7, which rounds up to 417 truck-days since you cannot have partial truck-days in practice.

Why the Other Options Are Wrong

Option A: 125 truck-days

This answer appears to result from dividing 15,000 by 12 (truck capacity per trip) and ignoring the 3 trips per day, giving 1,250 ÷ 10 = 125, which is an incorrect approach.

Option C: 1,250 truck-days

This answer is far too low and likely results from incorrectly dividing by the wrong factor or making a calculation error with the daily capacity per truck.

Memory Technique

Remember 'TDC' - Trips × Daily capacity = Capacity per truck-day, then divide Total volume by Capacity per truck-day

Reference Hint

Construction project management or earthwork sections covering equipment productivity and scheduling calculations

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.