A project manager discovers that the critical path has been delayed by 4 days due to late material delivery. The project was originally scheduled to complete in 120 days. What is the new project duration?

Correct Answer

D) 124 days

Since the critical path determines project duration, any delay to critical path activities directly extends the project completion date. A 4-day delay on the critical path extends the 120-day project to 124 days.

Answer Options
A
116 days
B
Cannot be determined without more information
C
120 days
D
124 days

Why This Is the Correct Answer

The critical path represents the longest sequence of activities that determines the minimum project duration. Any delay on the critical path directly impacts the overall project completion date because there is no float or slack time available. When the critical path is delayed by 4 days, the entire project duration must be extended by those same 4 days, making the new duration 120 + 4 = 124 days.

Why the Other Options Are Wrong

Option A: 116 days

This option is incorrect because we have sufficient information to determine the new duration. The critical path delay directly translates to project delay in a 1:1 ratio when no mitigation measures are implemented.

Option B: Cannot be determined without more information

This option incorrectly subtracts the delay from the original duration, which would suggest the project finishes earlier despite experiencing delays on the critical path.

Option C: 120 days

This option incorrectly assumes the project duration remains unchanged despite the critical path delay. The critical path has no float time, so any delay must extend the project completion date.

Memory Technique

Use the acronym 'CPD' - Critical Path Delay always equals Project Delay (unless you crash or fast-track to recover time).

Reference Hint

Look up 'Critical Path Method (CPM)' and 'Project Scheduling' in construction management chapters, typically found in project management or scheduling sections of contractor reference books.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.