A project has the following activities on the critical path: Foundation (4 days), Framing (12 days), Roofing (6 days), and Electrical rough-in (8 days). If the roofing activity is delayed by 2 days due to weather, what is the impact on project completion?

Correct Answer

B) 2-day delay in project completion

Since roofing is on the critical path and has zero float, any delay to this activity directly impacts the project completion date. A 2-day delay in roofing results in a 2-day delay in project completion.

Answer Options
A
No impact if other activities can be compressed
B
2-day delay in project completion
C
1-day delay in project completion
D
4-day delay in project completion

Why This Is the Correct Answer

Activities on the critical path have zero float, meaning any delay directly impacts the project completion date. Since roofing is specifically identified as being on the critical path, a 2-day weather delay will push the entire project completion back by exactly 2 days. There is no buffer time available to absorb this delay without affecting the final completion date.

Why the Other Options Are Wrong

Option A: No impact if other activities can be compressed

While activity compression (crashing) might theoretically be possible, the question asks for the direct impact of the roofing delay. Option A introduces a conditional scenario that wasn't presented in the problem, and compression would require additional resources and costs that aren't mentioned.

Option C: 1-day delay in project completion

A 1-day delay would only occur if there was 1 day of float available in the roofing activity, but since it's on the critical path, it has zero float. The full 2-day delay must be absorbed by extending the project completion date.

Option D: 4-day delay in project completion

A 4-day delay would suggest the impact is doubled, which has no basis in critical path methodology. The delay impact equals the actual delay duration when the affected activity is on the critical path with zero float.

Memory Technique

Critical = Zero float = Direct hit! Any delay on critical path activities hits the project completion date directly, one-for-one.

Reference Hint

Look up 'Critical Path Method (CPM)' and 'Float/Slack Time' in project management or scheduling chapters of construction management references

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.