EstatePass
Business & FinanceAccountinghard32% of exam part

A project has budgeted costs of $800,000 and actual costs to date of $480,000. The project is 55% complete. What is the projected cost variance at completion?

Correct Answer

D) $72,727 over budget

Projected total cost = Actual costs ÷ Percent complete = $480,000 ÷ 0.55 = $872,727. Cost variance = $872,727 - $800,000 = $72,727 over budget.

Answer Options
A
$145,455 over budget
B
$72,727 under budget
C
$27,273 over budget
D
$72,727 over budget

Why This Is the Correct Answer

To find the projected cost variance at completion, we first calculate the projected total cost by dividing actual costs by the percentage complete ($480,000 ÷ 0.55 = $872,727). Then we subtract the original budget from this projected total cost ($872,727 - $800,000 = $72,727). Since the projected cost exceeds the budget, this represents a cost overrun of $72,727.

Why the Other Options Are Wrong

Option B: $72,727 under budget

This amount appears to double the correct variance calculation. It may result from incorrectly calculating the variance as a percentage of remaining work rather than using the proper earned value formula.

Option C: $27,273 over budget

This option shows the correct dollar amount but incorrectly states 'under budget' when the project is actually over budget. The projected total cost of $872,727 exceeds the original budget of $800,000.

Memory Technique

Remember 'PACE': Projected = Actual ÷ Complete%. Then compare Projected to Budget to find variance direction.

Reference Hint

Look up 'Earned Value Management' or 'Cost Control' in project management chapters, specifically sections on Cost Performance Index (CPI) and Estimate at Completion (EAC)

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.