A project has budgeted costs of $200,000 and is 60% complete with actual costs of $140,000. What is the cost variance?
Correct Answer
A) $20,000 unfavorable
At 60% completion, budgeted costs should be $120,000 ($200,000 × 0.60). Actual costs are $140,000, creating an unfavorable variance of $20,000.
Why This Is the Correct Answer
Cost variance is calculated by comparing the budgeted cost for work performed (BCWP) against the actual cost of work performed (ACWP). At 60% completion, the budgeted cost should be $120,000 ($200,000 × 0.60). Since actual costs are $140,000, the project is over budget by $20,000. When actual costs exceed budgeted costs, this creates an unfavorable variance.
Why the Other Options Are Wrong
Option B: $80,000 favorable
This calculates the wrong variance amount - it appears to subtract the budgeted amount from actual costs incorrectly ($200,000 - $140,000 = $60,000)
Option C: $60,000 unfavorable
This shows both the wrong amount and wrong direction - actual costs exceed budget so it cannot be favorable, and the $80,000 figure has no basis in the calculation
Memory Technique
Remember 'AUF': Actual costs Under budget = Favorable, Actual costs Above budget = Unfavorable. Always multiply total budget by completion percentage first.
Reference Hint
Project Management chapter or Cost Control section - look for Earned Value Management (EVM) formulas and cost variance calculations
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
