EstatePass
Business & FinanceAccountinghard32% of exam part

A project has budgeted costs of $200,000 and is 60% complete with actual costs of $140,000. What is the cost variance?

Correct Answer

A) $20,000 unfavorable

At 60% completion, budgeted costs should be $120,000 ($200,000 × 0.60). Actual costs are $140,000, creating an unfavorable variance of $20,000.

Answer Options
A
$20,000 unfavorable
B
$80,000 favorable
C
$60,000 unfavorable
D
$20,000 favorable

Why This Is the Correct Answer

Cost variance is calculated by comparing the budgeted cost for work performed (BCWP) against the actual cost of work performed (ACWP). At 60% completion, the budgeted cost should be $120,000 ($200,000 × 0.60). Since actual costs are $140,000, the project is over budget by $20,000. When actual costs exceed budgeted costs, this creates an unfavorable variance.

Why the Other Options Are Wrong

Option B: $80,000 favorable

This calculates the wrong variance amount - it appears to subtract the budgeted amount from actual costs incorrectly ($200,000 - $140,000 = $60,000)

Option C: $60,000 unfavorable

This shows both the wrong amount and wrong direction - actual costs exceed budget so it cannot be favorable, and the $80,000 figure has no basis in the calculation

Memory Technique

Remember 'AUF': Actual costs Under budget = Favorable, Actual costs Above budget = Unfavorable. Always multiply total budget by completion percentage first.

Reference Hint

Project Management chapter or Cost Control section - look for Earned Value Management (EVM) formulas and cost variance calculations

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.