A project has actual costs of $180,000 and is 75% complete. The original budget was $220,000. Using the percentage of completion method, what is the projected final cost?
Correct Answer
B) $240,000
Projected final cost = Actual costs to date ÷ Percentage complete. $180,000 ÷ 0.75 = $240,000. This indicates the project will exceed the original budget by $20,000.
Why This Is the Correct Answer
The percentage of completion method calculates projected final cost by dividing actual costs to date by the percentage of work completed. With $180,000 spent at 75% completion, the formula gives us $180,000 ÷ 0.75 = $240,000. This projection indicates the project will exceed the original $220,000 budget by $20,000, which is a critical cost overrun that needs immediate attention.
Why the Other Options Are Wrong
Option A: $165,000
This amount would suggest the project is performing better than the original budget, but the calculation shows we're actually trending toward a cost overrun based on current spending rates.
Option D: $220,000
This represents the original budget amount, not the projected final cost based on current spending patterns. The original budget is irrelevant once we have actual performance data showing cost overruns.
Memory Technique
Think 'Actual ÷ Percent = Projected' - or remember 'APP' (Actual over Percent equals Projected). If you're 75% done but spent more than 75% of budget, you're headed for an overrun.
Reference Hint
Look up 'Project Cost Control' or 'Earned Value Management' sections in construction management chapters, typically found under project administration or cost estimating topics.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
