A project has activities with the following durations and dependencies: A(5 days), B(3 days, after A), C(7 days, after A), D(4 days, after B and C). What is the critical path duration?
Correct Answer
A) 16 days
The critical path is A→C→D (5+7+4=16 days) since path A→B→D only takes 12 days (5+3+4). The longest path determines the project duration.
Why This Is the Correct Answer
The critical path is the longest sequence of activities that determines the minimum project duration. To find it, we must calculate all possible paths from start to finish and identify the one with the greatest total duration. Path A→C→D takes 16 days (5+7+4), while path A→B→D takes only 12 days (5+3+4), making A→C→D the critical path at 16 days.
Why the Other Options Are Wrong
Option C: 14 days
12 days represents the duration of the shorter path A→B→D (5+3+4=12), not the critical path which must be the longest path through the network
Option D: 19 days
19 days would result from incorrectly adding all activity durations (5+3+7+4=19) without considering that activities B and C occur simultaneously after A, not sequentially
Memory Technique
Remember 'CRITICAL = LONGEST' - the critical path is always the path that takes the most time, creating the bottleneck for your entire project schedule
Reference Hint
Look up 'Critical Path Method (CPM)' or 'Project Scheduling' in construction management chapters, typically found in project management or scheduling sections
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
