EstatePass
Business & FinanceOperationsmedium10% of exam part

A project has activities A (3 days), B (5 days), C (4 days), and D (2 days). The sequence is A→B→D and A→C→D. What is the critical path duration?

Correct Answer

C) 10 days

Path A→B→D = 3+5+2 = 10 days. Path A→C→D = 3+4+2 = 9 days. The critical path is the longest path at 10 days.

Answer Options
A
11 days
B
14 days
C
10 days
D
9 days

Why This Is the Correct Answer

The critical path is the longest sequence of activities that determines the minimum project duration. To find it, we calculate the total duration of each possible path through the network. Path A→B→D takes 10 days (3+5+2) while path A→C→D takes 9 days (3+4+2). Since 10 days is longer, it becomes the critical path and determines the project duration.

Why the Other Options Are Wrong

Option A: 11 days

This represents the duration of path A→C→D (3+4+2 = 9 days), which is the shorter path and therefore not the critical path.

Option D: 9 days

This would be the result if you incorrectly added only activities A, B, and C (3+5+4 = 12 days), but this doesn't represent any valid path through the network since B and C are parallel activities.

Memory Technique

Remember 'CRITICAL = LONGEST' - the critical path is always the path that takes the longest time to complete, just like the most critical bottleneck in any process.

Reference Hint

Look up 'Critical Path Method (CPM)' or 'Project Scheduling' in construction management chapters, typically found in project management or scheduling sections.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.