A project has activities A (3 days), B (5 days), C (4 days), and D (2 days). The sequence is A→B→D and A→C→D. What is the critical path duration?
Correct Answer
C) 10 days
Path A→B→D = 3+5+2 = 10 days. Path A→C→D = 3+4+2 = 9 days. The critical path is the longest path at 10 days.
Why This Is the Correct Answer
The critical path is the longest sequence of activities that determines the minimum project duration. To find it, we calculate the total duration of each possible path through the network. Path A→B→D takes 10 days (3+5+2) while path A→C→D takes 9 days (3+4+2). Since 10 days is longer, it becomes the critical path and determines the project duration.
Why the Other Options Are Wrong
Option A: 11 days
This represents the duration of path A→C→D (3+4+2 = 9 days), which is the shorter path and therefore not the critical path.
Option D: 9 days
This would be the result if you incorrectly added only activities A, B, and C (3+5+4 = 12 days), but this doesn't represent any valid path through the network since B and C are parallel activities.
Memory Technique
Remember 'CRITICAL = LONGEST' - the critical path is always the path that takes the longest time to complete, just like the most critical bottleneck in any process.
Reference Hint
Look up 'Critical Path Method (CPM)' or 'Project Scheduling' in construction management chapters, typically found in project management or scheduling sections.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
