EstatePass
Business & FinanceAccountinghard32% of exam part

A job has budgeted costs of $280,000 and is 65% complete. Actual costs incurred to date are $195,000. What is the projected cost variance at completion?

Correct Answer

C) $20,000 over budget

Projected total cost = $195,000 ÷ 0.65 = $300,000. Cost variance = $300,000 - $280,000 = $20,000 over budget.

Answer Options
A
$15,000 under budget
B
$85,000 under budget
C
$20,000 over budget
D
$15,000 over budget

Why This Is the Correct Answer

To find projected cost variance at completion, first calculate the projected total cost by dividing actual costs by percent complete: $195,000 ÷ 0.65 = $300,000. Then compare this to the budgeted cost: $300,000 - $280,000 = $20,000 over budget. This method assumes the current cost performance trend will continue through project completion.

Why the Other Options Are Wrong

Option A: $15,000 under budget

This answer of $85,000 under budget is completely incorrect. It appears to subtract actual costs from budget ($280,000 - $195,000 = $85,000) without considering the completion percentage or projecting final costs.

Option B: $85,000 under budget

This answer incorrectly calculates the variance as $15,000. The error likely comes from miscalculating either the projected total cost or making an arithmetic mistake in the final variance calculation.

Option D: $15,000 over budget

This answer shows $15,000 under budget, which is both the wrong amount and wrong direction. The project is actually trending over budget, not under budget, based on current spending patterns.

Memory Technique

Remember 'Project to Complete': Actual costs ÷ Percent complete = Projected total cost. Then subtract original budget for variance.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.