A grading plan shows contour lines at 2-foot intervals. If you count 6 contour lines between two points that are 240 feet apart horizontally, what is the slope percentage between these points?
Correct Answer
C) 5%
The elevation change is 6 contour lines × 2 feet = 12 feet. Slope percentage = (rise/run) × 100 = (12/240) × 100 = 5%. This represents a relatively gentle slope.
Why This Is the Correct Answer
To calculate slope percentage, use the formula (rise/run) × 100. The rise is 6 contour lines × 2-foot intervals = 12 feet of elevation change. The run is the horizontal distance of 240 feet. Therefore: (12 ÷ 240) × 100 = 0.05 × 100 = 5%. This represents a gentle slope commonly found in residential grading projects.
Why the Other Options Are Wrong
Option A: 10%
This answer incorrectly calculates the slope as 10%. This error likely comes from miscalculating the elevation change or horizontal distance. The correct calculation is (12 ÷ 240) × 100 = 5%, not 10%.
Option B: 12%
This answer of 12% is incorrect and may result from confusing the total elevation change (12 feet) with the slope percentage. The slope percentage requires dividing rise by run, then multiplying by 100.
Option D: 15%
This answer of 15% is incorrect and significantly overestimates the slope. This error might occur from incorrectly calculating either the rise or run values, or from misunderstanding the slope percentage formula.
Memory Technique
Remember 'Rise over Run times 100' - like climbing stairs: count the vertical steps (rise), measure the horizontal distance (run), then convert to percentage.
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?