A grading plan shows contour lines at 2-foot intervals. If you count 6 contour lines between two points that are 240 feet apart horizontally, what is the slope percentage between these points?

Correct Answer

C) 5%

The elevation change is 6 contour lines × 2 feet = 12 feet. Slope percentage = (rise/run) × 100 = (12/240) × 100 = 5%. This represents a relatively gentle slope.

Answer Options
A
10%
B
12%
C
5%
D
15%

Why This Is the Correct Answer

To calculate slope percentage, use the formula (rise/run) × 100. The rise is 6 contour lines × 2-foot intervals = 12 feet of elevation change. The run is the horizontal distance of 240 feet. Therefore: (12 ÷ 240) × 100 = 0.05 × 100 = 5%. This represents a gentle slope commonly found in residential grading projects.

Why the Other Options Are Wrong

Option A: 10%

This answer incorrectly calculates the slope as 10%. This error likely comes from miscalculating the elevation change or horizontal distance. The correct calculation is (12 ÷ 240) × 100 = 5%, not 10%.

Option B: 12%

This answer of 12% is incorrect and may result from confusing the total elevation change (12 feet) with the slope percentage. The slope percentage requires dividing rise by run, then multiplying by 100.

Option D: 15%

This answer of 15% is incorrect and significantly overestimates the slope. This error might occur from incorrectly calculating either the rise or run values, or from misunderstanding the slope percentage formula.

Memory Technique

Remember 'Rise over Run times 100' - like climbing stairs: count the vertical steps (rise), measure the horizontal distance (run), then convert to percentage.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.