A general contractor is experiencing delays in concrete delivery that could impact the critical path. What is the BEST immediate action to take?
Correct Answer
B) Expedite materials from an alternate supplier
When critical path activities are threatened, the immediate priority is to expedite materials from alternate sources to minimize project delays. Other options may be necessary later but don't address the immediate scheduling crisis.
Why This Is the Correct Answer
Option B is correct because when critical path activities are threatened by material delays, the immediate priority is to maintain project schedule momentum. Expediting materials from alternate suppliers directly addresses the root cause of the delay and minimizes impact to the critical path. This proactive approach demonstrates proper project management by taking immediate corrective action rather than waiting or accepting delays.
Why the Other Options Are Wrong
Option A: Reschedule all subsequent activities
Negotiating a time extension with the owner is premature and reactive - it accepts defeat before attempting to solve the immediate problem and maintain the schedule.
Option C: Negotiate a time extension with the owner
Rescheduling all subsequent activities accepts the delay rather than trying to prevent it, and should only be done after exhausting options to maintain the original schedule.
Memory Technique
Think 'SAVE the critical path' - S.A.V.E. = Secure Alternate Vendors Expeditiously when materials threaten the schedule
Reference Hint
Project Management chapter - Critical Path Method (CPM) and schedule control procedures
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?