A general contractor is building a 5,000 sq ft warehouse. The project will disturb 2.5 acres of land. What NPDES permit requirement applies?

Correct Answer

C) Notice of Intent (NOI) for Construction General Permit

Construction activities that disturb one acre or more require a Notice of Intent (NOI) for coverage under the NPDES Construction General Permit. Since this project disturbs 2.5 acres, an NOI is required.

Answer Options
A
Individual NPDES permit required
B
No permit required
C
Notice of Intent (NOI) for Construction General Permit
D
State permit only, no federal permit needed

Why This Is the Correct Answer

The NPDES Construction General Permit requires a Notice of Intent (NOI) for any construction activity that disturbs one acre or more of land. Since this warehouse project disturbs 2.5 acres, it exceeds the one-acre threshold and therefore requires an NOI filing. This is a federal requirement under the Clean Water Act that applies to construction sites to prevent stormwater pollution from entering waterways.

Why the Other Options Are Wrong

Option B: No permit required

A permit is definitely required because the project disturbs 2.5 acres, which exceeds the one-acre threshold that triggers NPDES Construction General Permit requirements.

Option D: State permit only, no federal permit needed

Federal NPDES requirements apply in addition to any state permits. Construction activities disturbing one acre or more fall under federal Clean Water Act jurisdiction and require federal NPDES permit coverage.

Memory Technique

Think 'ONE and DONE' - One acre triggers the requirement, and NOI gets it done (Notice of Intent)

Reference Hint

Environmental regulations chapter or Clean Water Act/NPDES permit section in your reference materials

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.