EstatePass
Business & FinanceOperationshard10% of exam part

A general contractor discovers that concrete delivery is delayed by 2 weeks due to supplier issues. The concrete work is on the critical path and scheduled to start in 1 week. What is the best expediting strategy?

Correct Answer

D) Source concrete from multiple suppliers to meet the original schedule

Since the concrete work is on the critical path, the contractor should expedite by sourcing from multiple suppliers to meet the original schedule and avoid project delays. This maintains the critical path timeline.

Answer Options
A
Accept the delay and adjust the entire project schedule
B
Delay the concrete work and focus on other activities
C
Substitute with a different foundation system
D
Source concrete from multiple suppliers to meet the original schedule

Why This Is the Correct Answer

Option B is correct because when work on the critical path is threatened by delays, the primary strategy should be expediting to maintain the original schedule. Since concrete work is on the critical path, any delay will directly impact the project completion date. Sourcing from multiple suppliers is a practical expediting technique that can resolve the supply issue while keeping the project on track. This approach addresses the root problem (supplier delay) while maintaining schedule integrity.

Why the Other Options Are Wrong

Option A: Accept the delay and adjust the entire project schedule

Option D is wrong because delaying critical path activities automatically delays the entire project. While focusing on other activities might seem productive, it doesn't solve the fundamental problem and will still result in overall project delay.

Option C: Substitute with a different foundation system

Option A is wrong because accepting delays on critical path activities automatically extends the entire project duration. This should be a last resort after all expediting options have been exhausted, as it impacts project delivery commitments and may result in liquidated damages.

Memory Technique

Think 'Critical = Can't Wait' - critical path activities must be expedited, not delayed or substituted

Reference Hint

Project Management chapter - Critical Path Method (CPM) and schedule compression techniques

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.