EstatePass
Business & FinanceOperationsmedium10% of exam part

A general contractor discovers that a key material supplier will be 10 days late on delivery. The affected activities have 6 days of total float. What is the impact on the project completion date?

Correct Answer

C) 4-day delay in project completion

When a delay exceeds the available float, the project completion is delayed by the difference. Since the material delay is 10 days and available float is 6 days, the project will be delayed by 10-6=4 days.

Answer Options
A
6-day delay in project completion
B
10-day delay in project completion
C
4-day delay in project completion
D
No impact on project completion

Why This Is the Correct Answer

Option B is correct because when a delay exceeds the available float, the project completion date is impacted by the difference between the delay and the float. The material supplier delay of 10 days exceeds the 6 days of total float available for the affected activities. Therefore, the project completion will be delayed by 10 - 6 = 4 days. The float absorbs 6 days of the delay, but the remaining 4 days directly impact the critical path and project completion.

Why the Other Options Are Wrong

Option B: 10-day delay in project completion

Option D is wrong because it assumes the entire 10-day material delay directly impacts project completion, ignoring the protective effect of the 6 days of total float that can absorb part of the delay.

Option D: No impact on project completion

Option C is wrong because it assumes the entire float period becomes a delay, which is incorrect. The 6 days of float actually absorbs part of the 10-day delay, so only the excess (4 days) impacts project completion.

Memory Technique

Think 'Float First' - float always absorbs delay first, then any remaining delay hits the project completion. Use the acronym 'DAF' (Delay After Float) = Total Delay - Available Float.

Reference Hint

Project Management chapter covering Critical Path Method (CPM), Total Float, and Schedule Analysis

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.