A foundation plan shows a footing with reinforcement marked as '#5 @ 12" O.C.' What does this specification indicate?
Correct Answer
A) Number 5 rebar spaced 12 inches on center
#5 refers to number 5 rebar (5/8-inch diameter), and '@ 12" O.C.' means the bars are spaced 12 inches on center throughout the footing.
Why This Is the Correct Answer
The notation '#5 @ 12" O.C.' is standard construction terminology where the # symbol indicates rebar size number, not quantity. Number 5 rebar has a diameter of 5/8 inch. The '@' symbol means 'at' and 'O.C.' stands for 'on center,' which means the spacing is measured from the center of one bar to the center of the next bar. This creates a uniform 12-inch spacing pattern throughout the footing reinforcement.
Why the Other Options Are Wrong
Option B: 5/8-inch rebar with 12-inch overlap
This completely misunderstands the notation by interpreting '#5' as length (5-foot sections) rather than rebar size number. Rebar is typically sold in standard lengths and cut to fit, not specified in the reinforcement schedule this way.
Option C: 5-foot sections with 12-inch spacing
This interpretation incorrectly assumes the '#5' refers to quantity (5 pieces) rather than rebar size designation. The '12-inch depth' interpretation is also wrong since 'O.C.' specifically refers to spacing, not depth placement.
Option D: 5 pieces of rebar at 12-inch depth
This misinterprets both the rebar size and the spacing notation. While #5 rebar is indeed 5/8-inch diameter, the '12" O.C.' refers to center-to-center spacing, not overlap distance between bars.
Memory Technique
Think 'Number = Name, @ = At, O.C. = On Center' - so #5 @ 12" O.C. reads as 'Number 5 rebar at 12 inches on center spacing.'
Reference Hint
Florida Building Code, Chapter 19 - Concrete, or ACI 318 reinforcement tables for rebar sizing and spacing requirements
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass