A contractor submits a progress payment application for $75,000. The contract specifies a 10% retainage. If this is the final payment and half of the retained amount is released, what is the total payment amount?
Correct Answer
B) $71,250
Current payment after retainage: $75,000 × 90% = $67,500. Previously retained amount: $75,000 × 10% = $7,500. Half released: $7,500 ÷ 2 = $3,750. Total payment: $67,500 + $3,750 = $71,250.
Why This Is the Correct Answer
Option B correctly calculates the total payment by first determining the current payment after 10% retainage ($67,500), then adding half of the previously retained amount ($3,750). The final payment includes both the net current payment and the partial release of accumulated retainage. This reflects standard construction payment practices where final payments often include retainage releases.
Why the Other Options Are Wrong
Option A: $75,000
This represents the full gross payment amount without any retainage deduction, which would only occur if 100% of retainage was released and no current retainage was withheld.
Option D: $67,500
This amount exceeds the original payment application and would only be possible if more than the full retained amount was released, which contradicts the problem stating only half is released.
Memory Technique
Remember 'CPR': Current Payment + Retainage Release = Total payment. Current gets the retainage deduction, then add back any retainage release.
Reference Hint
Florida Building Code - Chapter 713 (Construction Liens) and AIA Contract Documents regarding payment and retainage provisions
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
