A contractor receives shop drawings from a steel fabricator that show connections different from the original structural drawings. What is the proper procedure?
Correct Answer
A) Submit the shop drawings to the engineer for review and approval
Shop drawings must be submitted to the engineer of record for review and approval before fabrication proceeds. Any deviations from the original design require engineering review to ensure structural integrity and code compliance.
Why This Is the Correct Answer
Shop drawings that deviate from the original structural drawings must be submitted to the engineer of record for review and approval before any fabrication proceeds. The engineer is the only qualified professional who can evaluate whether the proposed changes maintain structural integrity and comply with building codes. This is a standard industry practice that protects both the contractor and the project from potential structural failures or code violations. Any deviation from approved structural plans requires professional engineering review.
Why the Other Options Are Wrong
Option B: Modify the shop drawings to match the original drawings
The owner is not qualified to approve structural changes and does not have the technical expertise to evaluate structural integrity. Only the engineer of record has the authority and knowledge to approve deviations from structural drawings.
Option D: Contact the owner directly for approval
Proceeding with fabrication using shop drawings that differ from the original structural drawings without engineering approval is dangerous and potentially illegal. This could result in structural deficiencies, code violations, and liability issues for the contractor.
Memory Technique
Use the acronym 'SEAR' - Shop drawings with changes need Structural Engineer Approval Required
Reference Hint
Florida Building Code - Chapter 1, Administration and Enforcement, Section on Construction Documents and Shop Drawings
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass