A contractor receives a stop work order from OSHA for fall protection violations. The project has $180,000 remaining work. Estimated daily costs are $3,200 for labor, $1,800 for equipment, and $800 for overhead. If corrections take 4 days, what is the total cost impact?
Correct Answer
D) $23,200
Daily cost impact is $3,200 + $1,800 + $800 = $5,800. Over 4 days: $5,800 × 4 = $23,200. Stop work orders create significant financial impact through continued costs without production.
Why This Is the Correct Answer
The correct answer is B ($23,200) because when OSHA issues a stop work order, the contractor must continue paying daily operational costs even though no productive work can be performed. The daily cost impact includes all ongoing expenses: labor ($3,200), equipment ($1,800), and overhead ($800), totaling $5,800 per day. Multiplying this daily cost by the 4-day correction period gives $23,200 in total cost impact.
Why the Other Options Are Wrong
Option A: $27,600
Option C ($27,600) is incorrect because it overestimates the daily costs, possibly by including additional costs that aren't specified in the problem or miscalculating the daily total.
Option C: $31,200
Option A ($19,200) is incorrect because it appears to exclude one of the cost categories, possibly overhead costs, resulting in an incomplete calculation of the true daily cost impact.
Memory Technique
Think 'SWO = Still Writing Out checks' - Stop Work Orders mean you're still paying costs but getting no progress
Reference Hint
OSHA regulations and construction safety standards chapter, or project cost management and change order sections
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
