A contractor receives a stop work order from OSHA for fall protection violations. The project has a daily overhead cost of $2,800. If the stop work order lasts 5 days, what is the total overhead cost impact?
Correct Answer
C) $14,000
Total overhead cost = Daily overhead × Number of days = $2,800 × 5 days = $14,000. Stop work orders can result in significant financial impact due to continued overhead costs while work is halted.
Why This Is the Correct Answer
The correct answer is C) $14,000 because overhead costs continue to accumulate even when work is stopped due to regulatory violations. The calculation is straightforward: $2,800 daily overhead × 5 days = $14,000. This represents the total financial impact of overhead costs during the work stoppage period. Stop work orders don't eliminate overhead expenses like equipment rentals, supervision salaries, or site security costs.
Why the Other Options Are Wrong
Option A: $2,800
Option B ($11,200) appears to be calculated using 4 days instead of the specified 5 days ($2,800 × 4 = $11,200). This miscalculation underestimates the total overhead cost impact by one full day.
Option B: $16,800
Option A only represents one day's overhead cost ($2,800) and fails to account for the full 5-day duration of the stop work order. This significantly underestimates the financial impact of the work stoppage.
Option D: $11,200
Option D ($16,800) overestimates the cost by calculating 6 days instead of the specified 5 days ($2,800 × 6 = $16,800). This adds an extra day that wasn't part of the stop work order duration.
Memory Technique
Remember 'Daily × Days = Damage' - the financial damage from stop work orders equals daily overhead multiplied by the number of stopped days.
Reference Hint
Florida Building Code Chapter 1, Section 114 - Stop Work Orders, and construction project management sections covering overhead cost calculations
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
