EstatePass
Business & FinanceAccountingmedium32% of exam part

A contractor receives a $50,000 progress payment but owes $28,000 to subcontractors for that same work phase. The payment terms with subs require payment within 10 days. How should this be managed in accounts payable?

Correct Answer

C) Schedule payments to meet the 10-day terms while maintaining working capital

Proper accounts payable management requires honoring agreed payment terms to maintain good vendor relationships while strategically timing payments to optimize cash flow and maintain adequate working capital.

Answer Options
A
Hold payment for 30 days to improve cash flow
B
Negotiate extended payment terms with all subcontractors
C
Schedule payments to meet the 10-day terms while maintaining working capital
D
Pay all subcontractors immediately upon receipt of payment

Why This Is the Correct Answer

Option C represents proper accounts payable management by balancing contractual obligations with business needs. The contractor must honor the agreed 10-day payment terms to maintain good relationships with subcontractors and avoid potential legal issues. However, they should strategically schedule these payments within the allowed timeframe to maintain adequate working capital for ongoing operations and unexpected expenses.

Why the Other Options Are Wrong

Option A: Hold payment for 30 days to improve cash flow

While paying immediately shows good faith, it's not financially prudent as it doesn't optimize cash flow management. The contractor has 10 days to pay, so immediate payment upon receipt wastes the opportunity to maintain working capital for other business needs during that period.

Option B: Negotiate extended payment terms with all subcontractors

Attempting to negotiate extended terms after work is completed and payment is due is unprofessional and may damage relationships. Payment terms should be negotiated before work begins, not when payment is due.

Option D: Pay all subcontractors immediately upon receipt of payment

Holding payment for 30 days violates the agreed 10-day payment terms, which could damage vendor relationships, result in late fees, potential legal action, and may violate Florida construction payment laws that protect subcontractors.

Memory Technique

Remember 'HONOR & OPTIMIZE' - Honor your payment terms but Optimize your cash flow timing within those terms

Reference Hint

Florida Construction Industry Licensing Board study materials, Chapter on Business and Finance, Accounts Payable Management section

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.