EstatePass
Business & FinanceRegulationsmedium15% of exam part

A contractor is working on a project that will disturb 2.5 acres of land. The project involves grading and excavation that will expose soil. What NPDES permit requirement applies?

Correct Answer

B) General permit for stormwater discharge required

NPDES requires a general permit for stormwater discharge from construction activities that disturb one acre or more. The contractor must obtain coverage under the general permit and implement stormwater pollution prevention measures.

Answer Options
A
No permit required for projects under 3 acres
B
General permit for stormwater discharge required
C
Only local erosion control permit needed
D
Individual permit required for projects over 2 acres

Why This Is the Correct Answer

The National Pollutant Discharge Elimination System (NPDES) requires a general permit for stormwater discharge from construction activities that disturb one acre or more of land. Since this project disturbs 2.5 acres, it exceeds the one-acre threshold and requires NPDES general permit coverage. The contractor must submit a Notice of Intent (NOI) and develop a Stormwater Pollution Prevention Plan (SWPPP) before beginning construction activities.

Why the Other Options Are Wrong

Option A: No permit required for projects under 3 acres

This is incorrect because NPDES permit requirements are triggered at one acre, not three acres. Any construction activity disturbing one acre or more requires NPDES general permit coverage.

Option C: Only local erosion control permit needed

This is incorrect because individual NPDES permits are typically required for much larger projects or those with special circumstances, not simply projects over 2 acres. Most construction projects use the general permit regardless of size above the one-acre threshold.

Option D: Individual permit required for projects over 2 acres

This is incorrect because federal NPDES requirements supersede local permits alone. While local erosion control permits may also be required, they do not satisfy the federal NPDES stormwater discharge permit requirement for projects disturbing one acre or more.

Memory Technique

Remember 'ONE and DONE' - ONE acre triggers the requirement, and most projects are DONE with just the general permit (not individual permits)

Reference Hint

Look up NPDES stormwater regulations in the Environmental Regulations chapter or Water Quality/Stormwater Management section of your reference materials

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.