EstatePass
Project MgmtSafetyhard20% of exam part

A contractor is renovating a building constructed in 1975 and must disturb more than 260 linear feet of friable asbestos-containing material. What notification requirement must be met?

Correct Answer

B) Notify EPA at least 10 working days before starting

EPA requires notification at least 10 working days before beginning renovation or demolition activities that will disturb more than 260 linear feet of friable asbestos-containing material. This allows proper oversight and compliance verification.

Answer Options
A
No notification required
B
Notify EPA at least 10 working days before starting
C
Notify EPA at least 5 working days before starting
D
Notify only after work is completed

Why This Is the Correct Answer

The EPA's National Emission Standards for Hazardous Air Pollutants (NESHAP) requires notification at least 10 working days before beginning renovation or demolition activities that will disturb more than 260 linear feet of friable asbestos-containing material. This advance notification period allows the EPA to review the project, ensure proper procedures are in place, and conduct inspections if necessary. The 10-day requirement is specifically designed to provide adequate time for regulatory oversight and compliance verification before any asbestos disturbance occurs.

Why the Other Options Are Wrong

Option A: No notification required

While 5 working days might seem reasonable, the EPA specifically requires 10 working days advance notice, not 5. This longer timeframe ensures adequate time for regulatory review and potential inspection scheduling before work begins.

Option C: Notify EPA at least 5 working days before starting

Notification is absolutely required when disturbing more than 260 linear feet of friable asbestos-containing material. The EPA has strict regulations under NESHAP that mandate advance notification for projects exceeding this threshold to protect public health and ensure proper asbestos handling procedures.

Option D: Notify only after work is completed

Post-work notification is completely inadequate and violates EPA regulations. The purpose of advance notification is to allow oversight and prevention of improper asbestos handling, which cannot be achieved if notification occurs only after work is completed.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.