A contractor is renovating a building constructed in 1975 and must disturb more than 260 linear feet of friable asbestos-containing material. What notification requirement must be met?
Correct Answer
B) Notify EPA at least 10 working days before starting
EPA requires notification at least 10 working days before beginning renovation or demolition activities that will disturb more than 260 linear feet of friable asbestos-containing material. This allows proper oversight and compliance verification.
Why This Is the Correct Answer
The EPA's National Emission Standards for Hazardous Air Pollutants (NESHAP) requires notification at least 10 working days before beginning renovation or demolition activities that will disturb more than 260 linear feet of friable asbestos-containing material. This advance notification period allows the EPA to review the project, ensure proper procedures are in place, and conduct inspections if necessary. The 10-day requirement is specifically designed to provide adequate time for regulatory oversight and compliance verification before any asbestos disturbance occurs.
Why the Other Options Are Wrong
Option A: No notification required
While 5 working days might seem reasonable, the EPA specifically requires 10 working days advance notice, not 5. This longer timeframe ensures adequate time for regulatory review and potential inspection scheduling before work begins.
Option C: Notify EPA at least 5 working days before starting
Notification is absolutely required when disturbing more than 260 linear feet of friable asbestos-containing material. The EPA has strict regulations under NESHAP that mandate advance notification for projects exceeding this threshold to protect public health and ensure proper asbestos handling procedures.
Option D: Notify only after work is completed
Post-work notification is completely inadequate and violates EPA regulations. The purpose of advance notification is to allow oversight and prevention of improper asbestos handling, which cannot be achieved if notification occurs only after work is completed.
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
