A contractor is managing a project with the following critical path activities: A(5 days) → B(8 days) → C(6 days) → D(4 days). If Activity B is delayed by 3 days, what is the new project duration?
Correct Answer
A) 26 days
Original critical path duration: 5 + 8 + 6 + 4 = 23 days. With a 3-day delay in Activity B (which is on the critical path), the new project duration becomes 23 + 3 = 26 days.
Why This Is the Correct Answer
The critical path method requires calculating the total duration by adding all sequential activities. The original critical path duration is 5 + 8 + 6 + 4 = 23 days. Since Activity B is on the critical path, any delay to it directly extends the overall project duration. A 3-day delay to Activity B increases the total project duration from 23 days to 26 days.
Why the Other Options Are Wrong
Option B: 29 days
23 days is the original project duration before any delays were applied to Activity B.
Option C: 20 days
20 days represents a project duration that is 3 days shorter than the original 23-day duration, which makes no sense when a delay has occurred.
Option D: 23 days
29 days incorrectly adds the 3-day delay twice or uses faulty math, resulting in an excessive project duration.
Memory Technique
Remember 'Critical = Direct Impact' - any delay on the critical path directly adds to project duration, while delays on non-critical activities may have float time to absorb the delay.
Reference Hint
Project Management chapter, specifically Critical Path Method (CPM) and schedule analysis sections
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
