EstatePass
Business & FinanceOperationsmedium10% of exam part

A contractor is managing a project with the following critical path activities: A(5 days) → B(8 days) → C(6 days) → D(4 days). If Activity B is delayed by 3 days, what is the new project duration?

Correct Answer

A) 26 days

Original critical path duration: 5 + 8 + 6 + 4 = 23 days. With a 3-day delay in Activity B (which is on the critical path), the new project duration becomes 23 + 3 = 26 days.

Answer Options
A
26 days
B
29 days
C
20 days
D
23 days

Why This Is the Correct Answer

The critical path method requires calculating the total duration by adding all sequential activities. The original critical path duration is 5 + 8 + 6 + 4 = 23 days. Since Activity B is on the critical path, any delay to it directly extends the overall project duration. A 3-day delay to Activity B increases the total project duration from 23 days to 26 days.

Why the Other Options Are Wrong

Option B: 29 days

23 days is the original project duration before any delays were applied to Activity B.

Option C: 20 days

20 days represents a project duration that is 3 days shorter than the original 23-day duration, which makes no sense when a delay has occurred.

Option D: 23 days

29 days incorrectly adds the 3-day delay twice or uses faulty math, resulting in an excessive project duration.

Memory Technique

Remember 'Critical = Direct Impact' - any delay on the critical path directly adds to project duration, while delays on non-critical activities may have float time to absorb the delay.

Reference Hint

Project Management chapter, specifically Critical Path Method (CPM) and schedule analysis sections

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.