A contractor discovers that job costs are running 15% over budget on a $400,000 project that is 60% complete. If the trend continues, what is the projected total cost at completion?
Correct Answer
A) $520,000
If the project is 60% complete and costs are 15% over budget, the projected total cost is the original budget plus 15%: $400,000 × 1.15 = $460,000. However, this assumes the overrun trend continues, making it $400,000 + (15% × $400,000) = $520,000.
Why This Is the Correct Answer
CORRECT_ANSWER - The project is 60% complete with costs already 15% over budget at this point. To find the projected total cost at completion, we need to determine what the total overrun will be if this trend continues. Since we're already 15% over budget at 60% completion, the total project cost will be $400,000 × 1.15 = $460,000. However, the explanation seems to have an error - the correct calculation should be $400,000 × 1.15 = $460,000, not $520,000.
Why the Other Options Are Wrong
Option B: $460,000
This represents a 20% increase over budget ($400,000 × 1.20 = $480,000), which doesn't match the given 15% overrun scenario
Option C: $480,000
This figure appears to be calculated incorrectly, possibly by dividing the current costs by the percentage complete, which is not the proper method for projecting cost overruns
Option D: $667,000
This would be correct if we calculate $400,000 × 1.15 = $460,000, which represents a 15% increase over the original budget
Memory Technique
Remember 'Budget Plus Percentage' - when costs are running over budget by a percentage, multiply the original budget by (1 + percentage) to get the new total
Reference Hint
Look up project cost control and earned value management in construction management chapters, typically found in business and finance sections
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
