EstatePass
Business & FinanceOperationsmedium10% of exam part

A contractor discovers that a critical material delivery will be delayed by 2 weeks. The activity has 5 days of float. What is the impact on the project completion date?

Correct Answer

D) 9 days delay to project completion

The material delay is 14 days (2 weeks), but the activity has 5 days of float. Therefore, the net delay to project completion is 14 - 5 = 9 days.

Answer Options
A
No delay to project completion
B
14 days delay to project completion
C
5 days delay to project completion
D
9 days delay to project completion

Why This Is the Correct Answer

CORRECT_ANSWER - When an activity is delayed, the float (slack time) acts as a buffer that absorbs part of the delay. The material delivery delay is 14 days total, but since the activity has 5 days of float available, this float can absorb 5 days of the delay. The remaining 9 days (14 - 5 = 9) will impact the critical path and delay project completion.

Why the Other Options Are Wrong

Option B: 14 days delay to project completion

This represents the total material delay without considering that float can absorb part of the delay. It ignores the fundamental purpose of float in project scheduling.

Option C: 5 days delay to project completion

This assumes the entire 14-day delay can be absorbed by the 5 days of float, which is mathematically impossible. Float can only absorb delays up to its available amount.

Memory Technique

Think 'Float = Safety Net': Total delay minus your safety net (float) equals what hits the project completion date

Reference Hint

Project Management chapter, specifically sections on Critical Path Method (CPM) and float/slack calculations

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.