EstatePass
Business & FinanceRegulationshard15% of exam part

A construction site will disturb 0.8 acres but is part of a larger development that will ultimately disturb 3.2 acres. What NPDES requirement applies to this phase?

Correct Answer

B) NOI required based on total planned disturbance

NPDES regulations require permits based on total planned disturbance for the entire project, not individual phases. Since the total development will disturb over 1 acre, an NOI is required even for phases under 1 acre.

Answer Options
A
Local permit only
B
NOI required based on total planned disturbance
C
No permit required since this phase is under 1 acre
D
Individual permit required

Why This Is the Correct Answer

NPDES stormwater regulations evaluate permit requirements based on the total planned disturbance for the entire common plan of development or sale, not individual construction phases. Since the overall project will disturb 3.2 acres (exceeding the 1-acre threshold), a Notice of Intent (NOI) for coverage under the Construction General Permit is required for all phases of the project. This prevents developers from circumventing permit requirements by artificially breaking projects into smaller phases that individually fall below the 1-acre threshold.

Why the Other Options Are Wrong

Option A: Local permit only

While local permits may also be required, NPDES is a federal program administered by EPA or authorized states. Federal stormwater requirements cannot be satisfied by local permits alone when the project exceeds the 1-acre threshold for total disturbance.

Option C: No permit required since this phase is under 1 acre

An individual NPDES permit is typically required for major industrial dischargers or complex projects that cannot be adequately covered by general permits. For standard construction stormwater runoff from a 3.2-acre development, the Construction General Permit with NOI coverage is the appropriate regulatory pathway.

Option D: Individual permit required

This option incorrectly focuses only on the individual phase disturbance (0.8 acres) rather than the total project disturbance. NPDES regulations specifically look at the cumulative impact of the entire development plan, making this interpretation a violation of federal stormwater requirements.

Memory Technique

Remember 'TOTAL TROUBLE' - if the TOTAL project disturbance exceeds 1 acre, you're in regulatory TROUBLE and need NPDES permits for all phases

Reference Hint

Florida Building Code Chapter 15 - Referenced Standards, or EPA NPDES Construction General Permit fact sheets

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.