EstatePass
Business & FinanceAccountinghard32% of exam part

A construction company completed 60% of a $500,000 project by year-end. Total costs incurred to date are $280,000, with estimated total costs of $420,000. Using the percentage-of-completion method, what is the gross profit recognized?

Correct Answer

D) $20,000

Revenue recognized = $500,000 × 60% = $300,000. Costs incurred = $280,000. Gross profit = $300,000 - $280,000 = $20,000. The percentage-of-completion method recognizes profit based on project completion percentage.

Answer Options
A
$80,000
B
$48,000
C
$300,000
D
$20,000

Why This Is the Correct Answer

Under the percentage-of-completion method, revenue is recognized proportionally based on project completion percentage. With 60% completion, revenue recognized equals $500,000 × 60% = $300,000. Gross profit is calculated as recognized revenue minus costs incurred to date, which equals $300,000 - $280,000 = $20,000. This method matches revenue recognition with actual project progress.

Why the Other Options Are Wrong

Option A: $80,000

$80,000 represents the total estimated profit for the entire project ($500,000 contract - $420,000 estimated total costs). This ignores the percentage-of-completion principle and would only be correct if 100% of the project were complete.

Option B: $48,000

$48,000 incorrectly calculates profit as if using the total estimated profit ($500,000 - $420,000 = $80,000) multiplied by 60% completion. This approach double-applies the percentage completion concept and doesn't follow the proper percentage-of-completion accounting method.

Memory Technique

Use 'PRC': Percentage × Revenue = Recognized revenue, then subtract Costs incurred to get profit. Think 'Progress Revenue minus Current costs equals Profit Recognized.'

Reference Hint

Look up 'Percentage-of-Completion Method' in accounting or construction management chapters, typically found under 'Revenue Recognition' or 'Construction Accounting' sections.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.