Project MgmtConstructionmedium63% of exam part

A concrete slab measuring 40 feet by 60 feet with a thickness of 6 inches requires how many cubic yards of concrete?

Correct Answer

B) 44.4 cubic yards

Calculate: 40' × 60' × 0.5' = 1,200 cubic feet. Divide by 27 cubic feet per cubic yard: 1,200 ÷ 27 = 44.4 cubic yards. Always convert inches to feet before calculating volume.

Answer Options
A
1,440 cubic yards
B
44.4 cubic yards
C
3,600 cubic yards
D
133.3 cubic yards

Why This Is the Correct Answer

Option A is correct because the calculation properly converts all measurements to feet first: 40' × 60' × 0.5' (6 inches = 0.5 feet) = 1,200 cubic feet. Then dividing by 27 cubic feet per cubic yard gives 1,200 ÷ 27 = 44.4 cubic yards. This follows the standard concrete volume calculation method used in construction.

Why the Other Options Are Wrong

Option A: 1,440 cubic yards

This answer results from forgetting to convert inches to feet, calculating 40 × 60 × 6 = 14,400, then dividing by 108 (incorrectly using cubic inches conversion). The error is mixing units - you cannot multiply feet by inches directly without proper conversion.

Option C: 3,600 cubic yards

This answer results from multiplying length × width only (40 × 60 = 2,400) and then adding some arbitrary factor, or from completely incorrect unit conversions. It ignores the thickness dimension entirely or uses wrong conversion factors.

Memory Technique

Remember 'ICY 27': Inches to feet, Calculate volume, Yards by dividing by 27. Always convert thickness from inches to feet first (divide by 12), then multiply length × width × thickness for cubic feet, finally divide by 27 for cubic yards.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.