A building permit application is submitted on Monday for a $75,000 residential addition. According to typical Florida building department procedures, what is the standard timeframe for permit review?
Correct Answer
B) 10-15 business days
Most Florida building departments require 10-15 business days for standard residential permit reviews, though this can vary by jurisdiction and project complexity.
Why This Is the Correct Answer
CORRECT_ANSWER - Florida building departments typically require 10-15 business days for standard residential permit reviews for projects like a $75,000 addition. This timeframe allows sufficient time for plan review, code compliance verification, and coordination between different departments (building, electrical, plumbing, etc.). The complexity of a residential addition requires more thorough review than simple repairs but less than major commercial projects.
Why the Other Options Are Wrong
Option A: 7-10 business days
3-5 business days is too short for a comprehensive review of a $75,000 residential addition. This timeframe might apply to simple permits like minor repairs or over-the-counter permits, but not for additions requiring structural, electrical, and plumbing reviews.
Option D: 15-30 business days
15-30 business days is excessive for a standard residential addition and more typical of complex commercial projects or major developments requiring extensive review and coordination with multiple agencies.
Memory Technique
Think '10-15 for Residential' - the middle range for middle-complexity projects. Simple work gets quick review, complex work takes longer, residential additions fall in the middle.
Reference Hint
Florida Building Code Administration chapter or local building department procedures manual - look for 'Permit Processing Times' or 'Plan Review Procedures' sections
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?