A borrower submits a complete mortgage application on Tuesday at 2:00 PM. When is the latest the lender can deliver the Loan Estimate without violating TRID timing requirements?

Correct Answer

B) Friday by close of business

Under TRID, the 3-business day period begins the business day after application receipt. Tuesday application means Wednesday (day 1), Thursday (day 2), Friday (day 3). The Loan Estimate must be delivered by Friday's close of business.

Answer Options
A
Thursday by close of business
B
Friday by close of business
C
Saturday by close of business
D
Monday by close of business

Why This Is the Correct Answer

Under TRID, the 3-business day period begins the business day after application receipt. Tuesday application means Wednesday (day 1), Thursday (day 2), Friday (day 3). The Loan Estimate must be delivered by Friday's close of business.