A borrower receives a Loan Estimate on Wednesday and wants to proceed with the loan. Under TRID, what is the earliest date the borrower can close on the loan?
Correct Answer
D) The following Monday
Under TRID regulations (12 CFR 1026.19(f)(1)(iii)), there must be a 7-business day waiting period between when the Loan Estimate is received and closing. If received on Wednesday, counting 7 business days forward (excluding weekends), the earliest closing would be the following Monday.
Why This Is the Correct Answer
Under TRID regulations (12 CFR 1026.19(f)(1)(iii)), there must be a 7-business day waiting period between when the Loan Estimate is received and closing. If received on Wednesday, counting 7 business days forward (excluding weekends), the earliest closing would be the following Monday.
More Federal Laws Questions
A mortgage broker's website states 'Qualified borrowers can get loans with down payments as low as 3%.' Which statement about TILA advertising requirements is correct?
A loan's APR increases from 4.25% on the Loan Estimate to 4.35% on the Closing Disclosure due to a rate lock expiration. What action is required?
A lender originates a mortgage that meets all QM requirements. Three years later, the borrower defaults and claims the lender violated the ATR rule. What legal protection does the lender have?
For a closed-end mortgage loan, when must the creditor provide the Closing Disclosure to the borrower?
Which of the following documents must be provided to trigger the start of the 3-day rescission period?
People Also Study
General Mortgage Knowledge
23% of exam
Mortgage Loan Origination Activities
25% of exam
Ethics, Fraud & Consumer Protection
17% of exam
Uniform State Test Content
12% of exam
Previous Question
For HMDA reporting purposes, how should a lender classify a loan application that was withdrawn by the applicant after the lender requested additional documentation?
Next Question
A borrower's loan amount increases from $400,000 to $425,000 due to additional loan costs discovered during underwriting. The original Closing Disclosure was provided 5 business days before the scheduled closing. What action must the lender take?