EstatePass
Land Use & PlanningDevelopment ApprovalsABMEDIUM

Under Alberta's Municipal Government Act, what is the maximum timeframe a municipality has to make a decision on a complete development permit application?

Correct Answer

C) 40 days

Alberta's Municipal Government Act requires municipalities to make a decision on a complete development permit application within 40 days of submission. This timeframe ensures timely processing while allowing adequate time for review and public consultation if required.

Answer Options
A
20 days
B
60 days
C
40 days
D
90 days

Why This Is the Correct Answer

Option C is correct because Alberta's Municipal Government Act specifically mandates that municipalities must make a decision on a complete development permit application within 40 days of submission. This statutory timeframe is designed to ensure timely processing while providing sufficient time for proper review, technical analysis, and any required public consultation. The 40-day period begins when a complete application is received and includes all necessary supporting documentation and fees.

Why the Other Options Are Wrong

Deep Analysis of This Land Use & Planning Question

Background Knowledge for Land Use & Planning

Memory Technique

Exam Tip for Land Use & Planning

Real World Application in Land Use & Planning

Common Mistakes to Avoid on Land Use & Planning Questions

Key Terms

Municipal Government Actdevelopment permit40 daysAlbertacomplete application
Was this explanation helpful?

More Land Use & Planning Questions

People Also Study

Practice More Land Use & Planning Questions

Access 540+ Canadian real estate exam questions and pass your licensing exam.

Start Practicing