Under the NSW planning system, which development pathway typically has the shortest assessment timeframe?

Correct Answer

D) Complying development

Complying development is a fast-track pathway in NSW for low-impact development that meets pre-set standards in a state policy (mainly the Exempt and Complying Development Codes SEPP). A council or a registered certifier can issue a complying development certificate without a merit assessment or public exhibition, so it is usually the quickest approval. Integrated, designated and state significant development all involve extra assessment and take longer.

Answer Options
A
Integrated development
B
State significant development
C
Designated development
D
Complying development

Why This Is the Correct Answer

Complying development is checked against fixed, pre-set standards rather than assessed on its merits, and a council or registered certifier can issue the certificate without public exhibition, which makes it the quickest pathway.

Why the Other Options Are Wrong

Deep Analysis of This Planning Environment Question

Background Knowledge for Planning Environment

Memory Technique

Exam Tip for Planning Environment

Real World Application in Planning Environment

Common Mistakes to Avoid on Planning Environment Questions

Related Topics & Key Terms

Key Terms:

complying developmentassessment timeframesplanning legislationdevelopment standardsstreamlined approval
Was this explanation helpful?

More Planning Environment Questions

People Also Study

Practice More AU Questions

Access 1,100+ Australian real estate practice questions and ace your Certificate IV.

Browse All AU Questions