Four Forecasts, One Project

Sign in to watch1:46

The full transcript is below. To watch, create a free account: it comes with two lesson unlocks.

Chapters

  1. 0:00Question
  2. 0:32Breakdown
  3. 1:26Rule

In short

Earned value management forecasts a project's final cost from its performance to date. When cost efficiency is expected to continue, estimate at completion = budget at completion ÷ CPI, where CPI = earned value ÷ actual cost. With a $1,200,000 budget, $480,000 earned and $540,000 spent, the estimate is $1,350,000.

  • CPI = EV ÷ AC; SPI = EV ÷ PV.
  • Efficiency continues: EAC = BAC ÷ CPI.
  • One-off overrun: EAC = AC + (BAC − EV).

Transcript

0:00Question

Four forecasts for one project. Only one matches the assumption in the question. Lilly Pilly Health is fitting out a clinic on a budget of $1.2 million. So far it has done $480,000 of work, and spent $540,000 doing it. And the cost efficiency so far is expected to continue. What's the estimate at completion? Pick one.

0:32Breakdown

Earned value asks one thing first: how much work did each dollar buy? $480,000 of work for $540,000 spent. That's a cost index of about 0.89. If that efficiency continues, the whole budget stretches by the same ratio. $1.2 million, times 540 over 480: $1.35 million. A adds the gap between spending and the plan. That mixes cost with schedule. Cross out A. B divides by the schedule index, not the cost index. Cross out B. C finishes the rest on budget, as if the overrun stops today. Cross out C. D, $1.35 million.

1:26Rule

Read the assumption first. Efficiency continues? Divide by CPI. A one-off overrun? Actual cost, plus the budget for the work left. Want more traps like this? Follow for the next one.

Try a question on this lesson

From the EstatePass Strategic Management Accounting bank. Answer it, then read the explanation.

Question 1 of 10/0 correct

Lilly Pilly Health Ltd is fitting out a clinic with a budget at completion of $1,200,000. At the review date, planned value is $500,000, earned value is $480,000 and actual cost is $540,000. The project manager expects the cost efficiency achieved to date to continue for all remaining work. What is the estimate at completion?

Sources

  • PMI, Practice Standard for Earned Value Management
  • CPA question bank: cpa-sma-0411

Free lessons in other subjects

All CPA video lessons

Any companies and people in our lessons are fictional. EstatePass is not affiliated with CPA Australia; lessons and questions are our own, written from public standards and legislation.