Two months before the Firm Closing Date, a province-wide strike halts work on a new freehold home for six weeks. The builder told the buyer when the strike began, estimated how long it would last, and gave written notice when it ended. What does the Tarion addendum allow?

Correct Answer

B) The builder may extend deadlines by up to the length of the delay without paying compensation

A strike is an unavoidable delay under the Tarion addendum. If the builder informs the buyer at the outset, estimates the delay and gives written notice when it ends, it may extend deadlines by up to the length of the unavoidable delay period without paying delayed closing compensation.

Answer Options
A
The builder must pay $150 a day for every day that closing is late
B
The builder may extend deadlines by up to the length of the delay without paying compensation
C
The buyer may terminate the agreement at once and recover every deposit with interest
D
The builder may postpone closing indefinitely, because any strike cancels every addendum deadline

Why This Is the Correct Answer

Sign up free to unlock full analysis

Why the Other Options Are Wrong

Sign up free to unlock full analysis

Deep Analysis of This Residential Trading Question

Sign up free to unlock full analysis

Background Knowledge for Residential Trading

Sign up free to unlock full analysis
Sign up free to unlock full analysis

Real World Application in Residential Trading

Sign up free to unlock full analysis

Common Mistakes to Avoid on Residential Trading Questions

Sign up free to unlock full analysis

Key Terms

unavoidable delayTarion addendumstrikecritical datesdelayed closing
Was this explanation helpful?

More Residential Trading Questions

People Also Study

Practice More Residential Trading Questions

Access 540+ Canadian real estate exam questions and pass your licensing exam.

Start Practicing