EstatePass
Land Use & PlanningDevelopment ApprovalsONHARD

Under Ontario's Planning Act, a developer files a zoning by-law amendment application on the same day as a request to amend the official plan, because the rezoning also needs an official plan change. If council does not decide, after how many days from the clerk's receipt of the complete zoning application may the developer appeal it to the Ontario Land Tribunal?

Correct Answer

A) 120 days

Planning Act s. 34(11.0.0.0.1) applies when a zoning amendment would also require an official plan amendment and the application is made on the same day as the request to amend the official plan. In that case a non-decision appeal is available only if council fails to decide within 120 days after the clerk receives the application. A stand-alone zoning amendment uses 90 days under s. 34(11).

Answer Options
A
120 days
B
90 days
C
150 days
D
180 days

Why This Is the Correct Answer

The rezoning requires an official plan amendment and was filed the same day as that request, so s. 34(11.0.0.0.1) applies and the period is 120 days after the clerk receives the application.

Why the Other Options Are Wrong

Deep Analysis of This Land Use & Planning Question

Background Knowledge for Land Use & Planning

Memory Technique

Exam Tip for Land Use & Planning

Real World Application in Land Use & Planning

Common Mistakes to Avoid on Land Use & Planning Questions

Key Terms

zoning by-law amendmentofficial plan amendmentnon-decision appealOntario Land Tribunal120 days
Was this explanation helpful?

More Land Use & Planning Questions

People Also Study

Practice More Land Use & Planning Questions

Access 540+ Canadian real estate exam questions and pass your licensing exam.

Start Practicing