Under NSW planning legislation, what is the maximum time frame for a council to determine a standard development application?

Correct Answer

B) 40 days

Under the NSW Environmental Planning and Assessment Act 1979, councils have 40 days to determine a development application from the date it is lodged. This timeframe ensures timely processing while allowing adequate assessment time.

Answer Options
A
21 days
B
40 days
C
60 days
D
90 days

Why This Is the Correct Answer

Sign up free to unlock full analysis

Why the Other Options Are Wrong

Sign up free to unlock full analysis

Deep Analysis of This Planning Environment Question

Sign up free to unlock full analysis

Background Knowledge for Planning Environment

Sign up free to unlock full analysis
Sign up free to unlock full analysis

Real World Application in Planning Environment

Sign up free to unlock full analysis

Common Mistakes to Avoid on Planning Environment Questions

Sign up free to unlock full analysis

Related Topics & Key Terms

Key Terms:

Environmental Planning Assessment Actdevelopment application40 dayscouncil determinationNSW planning legislation
Was this explanation helpful?

More Planning Environment Questions

People Also Study

Practice More AU Questions

Access 520+ Australian real estate practice questions and ace your Certificate IV.

Browse All AU Questions