You receive three electrical subcontractor bids: Contractor A - $45,000 (excludes permits), Contractor B - $48,500 (includes all items), Contractor C - $44,200 (excludes temporary power). The permit cost is $800 and temporary power is $1,200. Which bid should be selected based on total cost?
Correct Answer
A) Contractor C at $45,400 total
Contractor A total: $45,000 + $800 = $45,800. Contractor B: $48,500 (complete). Contractor C: $44,200 + $1,200 = $45,400. Contractor C has the lowest total cost when all items are included.
Why This Is the Correct Answer
Contractor C has the lowest total cost when all items are properly included. To make an accurate comparison, all bids must be normalized to include the same scope of work. When we add the missing temporary power cost of $1,200 to Contractor C's base bid of $44,200, the total becomes $45,400, which is lower than both Contractor A's normalized total of $45,800 and Contractor B's complete bid of $48,500.
Why the Other Options Are Wrong
Option B: Contractor B at $48,500 total
Contractor A's total cost is $45,800 ($45,000 + $800 permit), which is $400 more than Contractor C's normalized total of $45,400.
Option C: All bids are equal when normalized
Contractor B's bid of $48,500 is the highest total cost, being $3,100 more than Contractor C's normalized total and $2,700 more than Contractor A's normalized total.
Memory Technique
Use 'ABC-Add Before Compare' - always Add missing costs Before Comparing bids to ensure apples-to-apples evaluation
Reference Hint
Florida Building Code Chapter 1 - Administration and Enforcement, and general contracting cost estimation sections in contractor reference materials
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A time and materials contract specifies labor at $85/hour and materials at cost plus 15%. If 40 hours of labor and $8,000 in materials are used, what is the total billing?
Next Question
Which of the following is NOT typically required to obtain a Certificate of Occupancy for a new restaurant?