Contract AdminPermitsmedium20% of exam part

Which of the following is NOT typically required to obtain a Certificate of Occupancy for a new restaurant?

Correct Answer

D) Contractor's final payment receipt

A contractor's final payment receipt is not required for a Certificate of Occupancy. The CO requires various agency approvals and inspections, but not proof of contractor payment.

Answer Options
A
Building department final inspection
B
Fire department final inspection
C
Health department approval
D
Contractor's final payment receipt

Why This Is the Correct Answer

A contractor's final payment receipt is a financial matter between the property owner and contractor, which has no bearing on the safety, code compliance, or operational readiness of the building. The Certificate of Occupancy process focuses on ensuring the structure meets all applicable codes and regulations for safe occupancy. Payment status between private parties is not a regulatory requirement and does not affect public safety or building compliance.

Why the Other Options Are Wrong

Option A: Building department final inspection

Building department final inspection is essential as it confirms the structure meets all building codes, electrical, plumbing, and mechanical systems are properly installed and safe for occupancy.

Option B: Fire department final inspection

Health department approval is mandatory for restaurants as they must comply with food service regulations, sanitation requirements, and public health codes before serving customers.

Option C: Health department approval

Fire department final inspection is absolutely required for a restaurant CO as it verifies fire suppression systems, emergency exits, occupancy loads, and other life safety requirements are properly installed and functional.

Memory Technique

Think 'SAFETY FIRST' - CO requires inspections that ensure safety (Fire, Health, Building), not financial paperwork (Payment receipts)

Reference Hint

Florida Building Code Chapter 1, Section 110 - Certificate of Occupancy requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.