EstatePass
Contract AdminContractseasy40% of exam part

In Florida, how long does a lienor have to file a Claim of Lien after the final furnishing of labor or materials?

Correct Answer

C) 90 days

Under Florida Statute 713.08, a Claim of Lien must be filed within 90 days after the final furnishing of labor, services, or materials by the lienor.

Answer Options
A
120 days
B
60 days
C
90 days
D
45 days

Why This Is the Correct Answer

Florida Statute 713.08 specifically establishes that a Claim of Lien must be filed within 90 days after the final furnishing of labor, services, or materials by the lienor. This 90-day period is a strict statutory deadline that cannot be extended. The statute is designed to provide a reasonable timeframe for lienors to perfect their lien rights while also providing certainty to property owners about when potential lien claims must be filed. Missing this 90-day deadline results in the complete loss of lien rights.

Why the Other Options Are Wrong

Option A: 120 days

45 days is too short and not the statutory requirement under Florida law

Option B: 60 days

120 days exceeds the statutory deadline and would be too late to file a valid lien claim

Option D: 45 days

60 days is insufficient time under Florida Statute 713.08

Memory Technique

Think '90 days = 3 months' - a full quarter of the year to file your lien claim, which seems like a reasonable middle ground between too short and too long

Reference Hint

Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.08

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.