EstatePass
Contract AdminContractsmedium40% of exam part

In arbitration proceedings for a construction dispute, the arbitrator's decision is generally:

Correct Answer

A) Binding and enforceable like a court judgment

Arbitration typically results in a binding decision that is enforceable like a court judgment. This is a key difference from mediation, where the mediator's role is to facilitate agreement rather than impose a decision.

Answer Options
A
Binding and enforceable like a court judgment
B
Only advisory unless both parties agree to be bound
C
Subject to appeal to a higher arbitration panel
D
A recommendation that either party can reject

Why This Is the Correct Answer

Arbitration produces a binding decision called an 'award' that has the same legal force as a court judgment. Once an arbitrator renders a decision, both parties are legally obligated to comply with it. The arbitrator acts as a private judge with the authority to make final, enforceable decisions. This binding nature is what makes arbitration an effective alternative dispute resolution method for construction disputes.

Why the Other Options Are Wrong

Option B: Only advisory unless both parties agree to be bound

This also describes mediation or non-binding arbitration. Standard arbitration is binding by default when parties agree to arbitrate - they don't need separate agreement to be bound by the decision.

Option C: Subject to appeal to a higher arbitration panel

Arbitration decisions are generally final with very limited grounds for appeal. Unlike court systems, there is no higher arbitration panel to appeal to - finality is a key feature of arbitration.

Memory Technique

Think 'ARBitration = ARBiter = judge-like authority = BINDING decision' vs 'MEDiation = MEDiator = middle person helping negotiate = non-binding'

Reference Hint

Florida Building Code Chapter 1, Section 113 - Alternative Dispute Resolution, or Construction Law reference materials on arbitration vs. mediation

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.