EstatePass
Contract AdminContractseasy40% of exam part

In a unit price contract, the contractor bids $125 per cubic yard for concrete placement. The original estimate was 400 cubic yards, but the actual quantity installed was 475 cubic yards. What is the total payment for concrete placement?

Correct Answer

B) $59,375

In a unit price contract, payment is based on actual quantities installed. 475 cubic yards × $125 per cubic yard = $59,375. The original estimate quantity is not used for payment calculations.

Answer Options
A
$62,500
B
$59,375
C
$57,500
D
$50,000

Why This Is the Correct Answer

In a unit price contract, payment is calculated by multiplying the actual quantity of work performed by the agreed-upon unit price. The contractor installed 475 cubic yards of concrete at $125 per cubic yard, resulting in a total payment of $59,375. The original estimate of 400 cubic yards is irrelevant for payment purposes - only the actual work completed matters in unit price contracts.

Why the Other Options Are Wrong

Option A: $62,500

This answer ($57,500) incorrectly uses the original estimated quantity of 400 cubic yards instead of the actual installed quantity (400 × $125 = $50,000 is not even this amount, so this may involve other calculation errors).

Option C: $57,500

This answer ($62,500) uses an incorrect unit price of approximately $131.58 per cubic yard, which is not the contracted rate of $125 per cubic yard.

Option D: $50,000

This answer ($50,000) appears to be calculated using an incorrect unit price of approximately $105 per cubic yard, or possibly using the wrong quantity altogether.

Memory Technique

Remember 'ACTUAL = PAYMENT' - in unit price contracts, you get paid for the actual work you do, not what you estimated you'd do.

Reference Hint

Florida Building Code - Chapter on Contract Types and Payment Methods, or Construction Contracting Business and Law reference materials covering unit price contracts

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.