EstatePass
Contract AdminContractseasy40% of exam part

In a cost-plus-fee contract, what is the contractor's primary obligation regarding project costs?

Correct Answer

B) To provide detailed documentation and accounting of all reimbursable costs

In cost-plus contracts, the contractor must maintain detailed records and provide transparent accounting of all costs since the owner reimburses actual costs plus a fee. This documentation is essential for payment and audit purposes.

Answer Options
A
To guarantee a maximum project cost
B
To provide detailed documentation and accounting of all reimbursable costs
C
To share cost savings equally with the owner
D
To absorb any cost overruns beyond the original estimate

Why This Is the Correct Answer

In cost-plus-fee contracts, the contractor is reimbursed for actual project costs plus a predetermined fee. Since the owner pays for actual costs rather than a fixed price, the contractor has a legal and contractual obligation to maintain meticulous records of all expenses. This documentation serves as proof of legitimate costs and enables proper reimbursement. Without detailed accounting, the owner cannot verify costs and the contractor cannot receive proper payment.

Why the Other Options Are Wrong

Option C: To share cost savings equally with the owner

In cost-plus contracts, the owner, not the contractor, typically absorbs cost overruns since they reimburse actual costs. The contractor is protected from cost risk, which is why detailed documentation is so crucial for reimbursement.

Option D: To absorb any cost overruns beyond the original estimate

Cost-plus contracts do not require contractors to guarantee maximum costs - that would be a guaranteed maximum price (GMP) contract. In pure cost-plus arrangements, costs can vary and the owner bears the risk of cost overruns.

Memory Technique

Think 'Cost-Plus = Paperwork Plus' - the contractor gets reimbursed PLUS a fee, but only with detailed paperwork to back up every cost

Reference Hint

Construction Contract Administration chapter or Project Delivery Methods section covering cost-plus contract types

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.