EstatePass
Contract AdminProcedureseasy13% of exam part

During construction, a water line was relocated 3 feet east from its original design location due to a rock formation. When should this change be documented on the as-built drawings?

Correct Answer

A) Immediately when the change is made in the field

Field changes should be documented on as-built drawings immediately when they occur to ensure accuracy and prevent information loss. This maintains an accurate record throughout the construction process.

Answer Options
A
Immediately when the change is made in the field
B
Only if the owner requests the information
C
At project completion when all as-builts are finalized
D
During the final inspection process

Why This Is the Correct Answer

As-built drawings must maintain real-time accuracy to serve their purpose as the definitive record of actual construction conditions. Documenting changes immediately when they occur prevents information loss, reduces errors, and ensures that all project stakeholders have access to current, accurate information. Waiting until later stages risks forgetting critical details, measurements, or the reasoning behind field changes, which could create serious problems for future maintenance, repairs, or modifications.

Why the Other Options Are Wrong

Option B: Only if the owner requests the information

Waiting until project completion to document changes creates significant risk of information loss, forgotten details, and inaccurate measurements. Field personnel may no longer be available, and the specific conditions that necessitated the change may be difficult to reconstruct.

Option C: At project completion when all as-builts are finalized

Documenting changes during final inspection is too late in the process. By this time, critical details may be forgotten, field conditions may have changed, and the opportunity to verify measurements and reasoning may be lost.

Option D: During the final inspection process

As-built documentation is a standard construction practice and professional responsibility, not dependent on owner requests. Contractors have a duty to maintain accurate records regardless of specific owner demands.

Memory Technique

Use the acronym 'NOW' - Note changes, Observe details, Write immediately. As-builts need to be updated NOW, not later.

Reference Hint

Florida Building Code, Chapter 1, Section 107 (Submittal Documents) and AIA Document A201 General Conditions, Article 3.11 (As-Built Documents)

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.