An owner and contractor have a dispute over $45,000 in additional work. The contract specifies that disputes under $50,000 must first go to mediation before litigation. The contractor wants to file a lawsuit immediately. What should happen?
Correct Answer
C) The court will likely require mediation first per the contract terms
When a contract specifies a dispute resolution process such as mandatory mediation before litigation, courts typically enforce these provisions and require parties to follow the contractual dispute resolution procedures before allowing litigation to proceed.
Why This Is the Correct Answer
Courts generally enforce contractual dispute resolution clauses as written, viewing them as valid agreements between parties. Since the contract specifically requires mediation for disputes under $50,000, and this dispute is $45,000, the mediation requirement applies. Courts will typically stay litigation proceedings until the contractual mediation process is completed, as parties are bound by the terms they agreed to in their contract.
Why the Other Options Are Wrong
Option B: The contractor can proceed directly to litigation since the amount exceeds $40,000
This option incorrectly suggests there's a $40,000 threshold that allows bypassing mediation, but the contract clearly states disputes under $50,000 must go to mediation first. The $45,000 dispute falls below the $50,000 threshold, so mediation is required regardless of any other amount.
Option D: The dispute must go to binding arbitration instead of court
When a contract contains mandatory dispute resolution language (like 'must first go to mediation'), neither party has the choice to bypass this requirement. The contractual obligation is binding on both parties, and courts will enforce the agreed-upon sequence of dispute resolution.
Memory Technique
Remember 'Contract Controls Courts' - when contracts specify dispute procedures, courts typically enforce them rather than allow parties to skip agreed-upon steps.
Reference Hint
Florida Construction Law - Chapter on Contract Dispute Resolution and Alternative Dispute Resolution (ADR) provisions
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
An experienced contractor is estimating productivity for installing drywall in a high-end residential project with many angles and custom details. Compared to standard productivity rates, the adjustment factor should be:
Next Question
When determining equipment costs for a project estimate, which factor most significantly affects the decision between purchasing and renting equipment?
