EstatePass
trade-general-buildingConcrete & MasonryMEDIUM

According to California Building Code requirements for concrete testing, what is the minimum frequency for taking compression test specimens during concrete placement?

Correct Answer

C) One set for every 100 cubic yards placed

CBC Section 1905.6.2.4 requires compression test specimens to be taken at a rate of not less than one set for every 100 cubic yards of concrete placed, with at least one set per day. This testing frequency ensures adequate quality control and compliance with specified concrete strength requirements throughout the project.

Answer Options
A
One set for every 50 cubic yards placed
B
One set for every 150 cubic yards placed
C
One set for every 100 cubic yards placed
D
One set per day of placement

Why This Is the Correct Answer

CBC Section 1905.6.2.4 requires compression test specimens at a minimum frequency of one set per 100 cubic yards of concrete placed, with at least one set per day of placement. This ensures ongoing quality verification throughout a pour and across the project duration.

Why the Other Options Are Wrong

Option A: One set for every 50 cubic yards placed

One set per 50 cubic yards is twice as frequent as required β€” it exceeds the minimum and would add unnecessary cost and testing burden. The CBC specifies 100 cubic yards as the threshold.

Option B: One set for every 150 cubic yards placed

One set per 150 cubic yards is less frequent than the 100-cubic-yard minimum requirement and would not meet CBC testing standards. Using this frequency could result in inadequate quality control.

Option D: One set per day of placement

One set per day of placement alone is insufficient as a standalone rule. While the CBC does include a one-set-per-day minimum, the primary frequency requirement is one set per 100 cubic yards. Large pours require more frequent sampling than once daily.

Memory Technique

100 yards, one set β€” every 100 cubic yards of concrete must be sampled. Think of a football field: 100 yards means time to test. And at minimum, test once per day no matter the volume.

Was this explanation helpful?

More trade-general-building Questions

When installing engineered lumber joists (I-joists) in California residential construction, what is the primary code requirement for web stiffeners?

What is the required attic ventilation ratio when a vapor retarder is installed on the warm-in-winter side of the ceiling according to the California Residential Code?

In California's Wildland-Urban Interface (WUI) areas, which underlayment requirement applies to Class A fire-rated roof assemblies?

In California, when installing a tankless water heater in a seismic zone, what additional requirement must be met beyond standard installation practices?

According to the California Building Code (CBC), what is the minimum lap splice length for #4 rebar in a concrete foundation wall in normal weight concrete with f'c = 3000 psi?

According to CBC requirements for retaining walls in California, what additional design consideration must be addressed for retaining walls over 4 feet in height located in seismic design categories D, E, and F?

When constructing retaining walls in California that exceed 4 feet in height, which CBC requirement must be met regarding drainage?

Under California regulations, when is a reduced pressure principle (RPP) backflow prevention assembly required for a residential water service connection?

Under California Title 24, what is the minimum electrical service size required for new single-family residential construction?

According to the California Building Code, buildings located in Seismic Design Category D must comply with which specific seismic design requirements?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.